20/05/2026
Phase 1 of new Mot station works.
The new area for the ramp formed with a 165mm drop from what will be the new finished floor level.
A total of 27T of material have been removed so far.
Area of bay dug down.
Prepared with 100mm compacted type1 and levelled with laser level.
Twin 1200 gauge dpm layer.
A193 mesh laid on semi engineering bricks
Concreted with 200mm of RC35 self compacting concrete, laser levelled checked before applying a dapple bar ensuring a finish to a 3mm tolerance across the slab and a lovely smooth finish ready for its epoxy coating at end of project.
Next on to the block-work to form the bay and digging out for brake rollers.