Timberline Spider

Timberline Spider MENZI MUCK A91 4X4 ALL TERRAIN EXCAVATOR

Spider Excavators provides first class services with better than expected results to your steep and challenging projects. From vegetation management to a wide range of steep slope excavating services, we have the comprehension and technology to provide the sought after complete solution to all your projects. In addition, Timberline Spider brings you the know-how expertise based on 20 years experience working in remote locations making the impossible happen.

Another good day in the mountains!
02/26/2025

Another good day in the mountains!

Securing our load. Heading to Kelowna
12/07/2024

Securing our load. Heading to Kelowna

10/23/2023

Take a peek at this shot taken between this fall’s extended closures 👀

Here at the west end of the Kicking Horse Canyon Phase 4 alignment, you can see about one-third of the entire project!

From bottom left to right: Sheep Bridge, Bighorn Wall and Viaduct, Bighorn Bridge, Lynx Viaduct, Frenchman’s Bridge and Viaduct, Cut 3, with Elk Viaduct and Grizzly Wall 2 in the distance.

Want to check out the full project alignment? Have a look at the alignment and structures key plan on our website: https://bit.ly/43QzEWb

WHY SPIDER EXCAVATORS?The Menzi Muck is a highly versatile and powerful tool that can work in water up to 1.7m deep whil...
10/18/2023

WHY SPIDER EXCAVATORS?
The Menzi Muck is a highly versatile and powerful tool that can work in water up to 1.7m deep while using biodegradable hydraulic fluid to protect water supply and fish habitat.
~
~
~


Closer up to the Spider M545X Action 🙌
10/13/2023

Closer up to the Spider M545X Action 🙌

How to remove a giant boulder.
10/11/2023

How to remove a giant boulder.

Team work!
10/04/2023

Team work!

09/06/2023

Here you can see the newly poured concrete deck at Sheep Bridge curing under wet burlap!

Get all the latest project news and info at https://bit.ly/3LrVCbf

04/28/2023

Earlier this month the removal of material at Cut 1 was completed.

Bighorn Viaduct and Bridge can be seen in the background of this photo taken on March 30.

The approaches to Bighorn Bridge will be completed this construction season!

Get all the latest project news and info at https://bit.ly/3KUKWQH

03/09/2023
Like father - like son 🤙 The Spider working at  improving an already great ski area. --
09/26/2022

Like father - like son 🤙
The Spider working at improving an already great ski area.
-
-

09/25/2022

The Fall 2022 extended closure begins at 12 pm (MT) on September 26 and continues until 6 am December 1.

Highways 93S and 95 may be used as alternate routes during this time.
The highway will reopen with no stoppages during the Thanksgiving holiday long weekend from 12 pm October 7 to 12 pm October 11.

Always check DriveBC.ca for the most current information.

See the full schedule on our Highway Status Calendar: http://ow.ly/mztw50Kw9yu

Address

Box 1512
Golden, BC
V0A1H0

Alerts

Be the first to know and let us send you an email when Timberline Spider posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Timberline Spider:

Share