06/19/2026
Progress continues at Red River Army Depot as our team advances through a major facility rehabilitation and structural improvement project. With only one concrete pour remaining before foundation completion and structural work now approximately 40% complete, we’re steadily building momentum toward the next phase of construction.
From foundation work to structural upgrades, our crews remain focused on delivering quality craftsmanship, maintaining safety standards, and keeping the project moving forward on schedule.