31/03/2022
Have you been following our R63 Alice construction project?
Take a look at where it’s at:
Services to Phase 1 & 2 of the Urban Section are 90% complete.
The base course Trial Section is complete.
Selected layers are 60% complete and subbase is currently being tipped.
The street lighting TE contractors are appointed.
Installation of storm water reticulation has commenced to Phase 3.
Bulk earthworks to the Rural Section is 92% complete and installation of drainage at 98%.
Subsoil drainage installation is 50% complete.
The deck widening to Contract RHS of the Kat River Bridge, was cast last year and staging is currently being dismantled.
Work on the Brak River Bridge is underway.
The deck to the Kwezana Rail Bridge will be cast this month.
The CD Project will commence early February.